Parking on Orheiului Street will have 178 spaces; paving nearing completion

Lighting is to be installed, while the video surveillance and access control systems are still being designed.

by 2 min read

Drafted with AI assistanceOriginal checked and approved by Vasile Ceban

Machine-translated from Română.Read the original

Listen to this article

AI-generated voice · ElevenLabs

Ask AI about this article

AI-generated illustration: Paving at the Calea Orheiului parking lot in Chișinău is nearly complete.
AI-generated illustration: Paving at the Calea Orheiului parking lot in Chișinău is nearly complete.AI-generated image · Moldova Comunică

In brief

  • Underground cables for public lighting have already been installed at the parking lot on Orheiului Street, according to Chișinău City Hall.
  • The park-and-ride lot on Codrilor Street is planned to have 250 spaces, and work is underway on the stormwater drainage system.
  • The parking lot on Ghidighici Street will have 240 spaces and is at the stage of underground cable installation.

Drivers arriving from outside Chișinău will be able to leave their cars in a 178-space parking lot on Orheiului Street and continue their journey by public transport. Chișinău City Hall said on 26 November 2026 that paving is nearing completion, but lighting and other improvements still need to be carried out.

What does this mean for you?

Park-and-ride lots are intended for drivers arriving from outside the city who want to leave their cars at the entrance to Chișinău. From there, they will be able to continue their journey by public transport instead of driving to the capital’s centre.

According to City Hall, this arrangement is expected to ease traffic congestion and reduce demand for parking spaces in the centre. The parking lots on Orheiului Street, Codrilor Street and Ghidighici Street are still being developed.

What work remains on Orheiului Street?

At the parking lot on Orheiului Street, crews are installing curbs and paving the remaining areas. The planned capacity for this parking lot is 178 spaces.

Underground cables for public lighting have been installed, and the next stage is installing poles and light fixtures. Landscaping and the installation of street furniture are also planned.

The video surveillance and access control systems are still at the design stage. According to City Hall, they will be installed at a later stage.

What stage are the parking lots on Codrilor and Ghidighici streets at?

Work on the stormwater drainage system is underway at the park-and-ride lot on Codrilor Street, which is planned to have 250 spaces. Development of this parking lot is continuing alongside work on Orheiului Street.

Underground cables are being installed at the parking lot on Ghidighici Street, which will have 240 spaces. They are intended to provide electricity and support access control and video surveillance.

Sources

  1. Primăria Chișinău — comunicate — Ultimele lucrări la parcarea de captură de pe Calea Orheiului

Written with AI assistance from the official sources above and checked by the editors.

What we checked (4 claims and their sources)

Every figure, date and name in the article, with the official source it comes from (in Romanian). Each claim is checked against its source automatically, then an editor approves the article.

  1. Primăria Chișinău a publicat informațiile despre stadiul lucrărilor pe 26 noiembrie 2026. — Primăria Chișinău — comunicate
  2. Parcarea de captură de pe Calea Orheiului va avea 178 de locuri. — Primăria Chișinău — comunicate
  3. Parcarea de captură de pe strada Codrilor va avea 250 de locuri. — Primăria Chișinău — comunicate
  4. Parcarea de captură de pe strada Ghidighici va avea 240 de locuri. — Primăria Chișinău — comunicate
RomânăРусский

Newsletter

Moldova, in your inbox

The stories that matter, every morning, in a single email. You choose what you get and in which language.

  • Free
  • No spam
  • One-click unsubscribe
What you want to receive
Email language