Technical assessment found advanced structural deterioration, with the rehabilitation project estimated to cost up to €10.7 million.

by 2 min read

Drafted with AI assistanceOriginal checked and approved by Vasile Ceban

Machine-translated from Română.Read the original

Listen to this article

AI-generated voice · ElevenLabs

Ask AI about this article

The Ismail Street bridge in Chișinău, viewed beside the railway, with its concrete structure visible.
The Ismail Street bridge in Chișinău, viewed beside the railway, with its concrete structure visible.AI-generated image · Moldova Comunică

In brief

  • According to Chișinău City Hall, a technical assessment classified the overall condition of the bridge on Ismail Street as category D, unsatisfactory.
  • The total cost of the Chișinău Urban Connectivity project is estimated at up to €10.7 million.
  • The bridge on Ismail Street crosses Albișoara Street and the Chișinău–Ungheni–Iași railway line.

Rehabilitation of the bridge on Ismail Street in Chișinău will have a preparatory phase supported by a pre-financing agreement with the European Bank for Reconstruction and Development (EBRD). The Chișinău Municipal Council (CMC) approved the agreement, according to information published by Chișinău City Hall on 5 November 2026.

What does the approved agreement cover?

The agreement between Chișinău Municipality and the EBRD concerns preparation of the Chișinău Urban Connectivity project, which will include rehabilitation of the bridge on Ismail Street. According to City Hall, the pre-financing makes it possible to start and advance the preparatory activities needed to implement the project.

The project’s total estimated cost is up to €10.7 million. This is an estimate for the entire project, not an amount stated separately for the pre-financing agreement.

What problems did the assessment identify?

The bridge on Ismail Street, built in 1968–1969, is in an unsatisfactory overall condition, classified as category D, according to the conclusions of the technical assessment presented by City Hall. The assessment identified advanced deterioration of structural elements.

The assessment included an examination of accessible parts of the structure, measurements and tests that do not damage the concrete, to check its strength. According to the assessment cited by the municipality, deterioration is progressing and affecting the bridge’s ability to carry loads, making rehabilitation work necessary.

What does this mean for you?

Rehabilitation of the bridge on Ismail Street aims to improve safety for road users and extend the period during which the structure can be used, according to City Hall. The municipality also lists reducing congestion and travel time among its objectives.

The planned work concerns the bridge that crosses Albișoara Street and the Chișinău–Ungheni–Iași railway line. The approved agreement concerns project preparation, while the municipality presents improved traffic flow as one of the rehabilitation’s objectives.

Sources

  1. Primăria Chișinău — comunicate — CMC a aprobat Acordul de prefinanțare dintre Municipiul Chișinău și Banca Europeană pentru Reconstrucție și Dezvoltare (BERD), în vederea reabilitării podului de pe strada Ismail 05.11.2026 20

Written with AI assistance from the official sources above and checked by the editors.

What we checked (6 claims and their sources)

Every figure, date and name in the article, with the official source it comes from (in Romanian). The check against sources is automatic, before editor approval.

  1. Primăria Chișinău a publicat informația despre aprobarea acordului pe 5 noiembrie 2026. — Primăria Chișinău — comunicate
  2. Consiliul Municipal Chișinău a aprobat decizia privind Acordul de prefinanțare dintre Municipiul Chișinău și Banca Europeană pentru Reconstrucție și Dezvoltare, pentru activitățile pregătitoare ale proiectului Conectivitate Urbană Chișinău. — Primăria Chișinău — comunicate
  3. Costul total estimat al proiectului Conectivitate Urbană Chișinău este de până la 10,7 milioane de euro. — Primăria Chișinău — comunicate
  4. Podul rutier de pe strada Ismail a fost construit în perioada 1968–1969. — Primăria Chișinău — comunicate
  5. Expertiza tehnică a clasificat starea generală a podului drept nesatisfăcătoare, categoria D, și a constatat degradări avansate ale elementelor structurale. — Primăria Chișinău — comunicate
  6. Podul de pe strada Ismail este situat deasupra străzii Albișoara și a liniei de cale ferată Chișinău–Ungheni–Iași. — Primăria Chișinău — comunicate
РусскийRomână

Newsletter

Moldova, in your inbox

The stories that matter, every morning, in a single email. You choose what you get and in which language.

  • Free
  • No spam
  • One-click unsubscribe
What you want to receive
Email language